Trans Mountain pipeline expansion cost jumps 70 per cent to $12.6 billion

Feb 7, 2020 | 10:32 AM

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.