Snow delays Wapiti Road upgrades
The snow means a delay in the completion of paving work along Wapiti Road.
The target date had been mid-October.
City capital construction supervisor Mark Hoseasson says the contractor is committed to finishing the project this year.
“As soon as we get a weather window. He figures he needs about four days of paving and then that will get the road back to fully operational, so then we’ll be able to get that part of the project completed. There is a little bit more of the box culvert that we have to do, but we’re outside of the roadway now, so that can continue.”