Site C dam cost grows to $16 billion – completion delayed by one year
VICTORIA – The cost of British Columbia’s Site C hydroelectric dam has grown by $6 billion, bringing the price tag of the megaproject to $16 billion and stretching the completion date to 2025.
The provincial government says the skyrocketing expenses are due to construction setbacks, geotechnical issues, COVID-19 and other cost and schedule pressures.
Premier John Horgan’s announcement comes weeks after a former deputy finance minister completed his report on the status of the northeastern B.C. dam and submitted the study for cabinet consideration.
The review was ordered last July after Crown-owned BC Hydro reported concerns about risks and delays, and the province says it has accepted all 17 of Peter Milburn’s recommendations, including a strengthened project assurance board.